Progress billing
G702 / G703 pay application worksheet
A sample HVAC job is loaded. Change This period on any line — current payment due updates live in the summary bar and G702 panel. Not an official AIA Contract Documents form.
Riverside Clinic — HVAC package
Application 3 · 2026-08-01 → 2026-08-31
Job complete
69.6%
Current payment due
$61,615.00
Payment due
$61,615.00
How to fill out G702 and G703 · What is a schedule of values · How to bill retainage
Questions this page answers
- What is AIA G702 and G703?
- G702 is the Application for Payment cover. G703 is the continuation sheet that lists the schedule of values line by line. Official forms are sold by AIA. This worksheet follows the same math.
- How do previous certificates for payment work?
- Line 7 is the total already certified. Current payment due is earned less retainage minus that total. If last month’s completed work is overwritten, Line 7 and Column D stop matching the GC.