G702 / G703 pay application worksheet

A sample HVAC job is loaded. Change This period on any line — current payment due updates live in the summary bar and G702 panel. Not an official AIA Contract Documents form.

Riverside Clinic — HVAC package

Application 3 · 2026-08-012026-08-31

Current payment due

$61,615.00

Application header
Project identity and billing period
$
$
Retainage settings
5.0% effective rate on this application

Rate

5.0%

Held

$10,735.00

Earned less retainage

$203,965.00

Schedule of values
G703 continuation sheet — edit this period to move payment due
#DescriptionScheduledPreviousThis periodStoredTo date%Balance
$12,000.00100%$0.00
$158,000.0085%$28,000.00
$40,500.0055%$33,500.00
$4,200.0015%$23,800.00
Totals$300,000.00$214,700.0070%

Line 1

$
$
$
$

To date

$12,000.00

Percent

100%

Balance

$0.00

Line 2

$
$
$
$

To date

$158,000.00

Percent

85%

Balance

$28,000.00

Line 3

$
$
$
$

To date

$40,500.00

Percent

55%

Balance

$33,500.00

Line 4

$
$
$
$

To date

$4,200.00

Percent

15%

Balance

$23,800.00

Payment due

$61,615.00

How to fill out G702 and G703 · What is a schedule of values · How to bill retainage

Questions this page answers

What is AIA G702 and G703?
G702 is the Application for Payment cover. G703 is the continuation sheet that lists the schedule of values line by line. Official forms are sold by AIA. This worksheet follows the same math.
How do previous certificates for payment work?
Line 7 is the total already certified. Current payment due is earned less retainage minus that total. If last month’s completed work is overwritten, Line 7 and Column D stop matching the GC.