Michigan public retainage is 10% until 50% complete
Michigan public retainage is the one that surprises 5%-habit estimators. MCL 125.1563 lets a public agency keep up to 10% of work in place until the job is 50% complete. After 50%, additional retainage is not withheld unless the agency finds unsatisfactory progress (then it may still keep up to 10% of the remaining work). Retained public funds belong in an interest-bearing account, and after about 94% complete a contractor can often swap an irrevocable letter of credit for the holdback.
Private Michigan retainage is still the subcontract. There is no statewide 5% private cap. Lien practice sits in MCL 570.1101 et seq. — do not treat public 10% rules as if they apply to a private plant job.
If the pay app is a Michigan public job, open the retainage calculator at 10% and turn on step-down only if the agency has actually stopped withholding after 50%. Then carry Line 5 forward on the G702-style worksheet so you are not re-withholding the first half of the job.
Statute text: Mich. Comp. Laws § 125.1563. Confirm the current code before you rely on a date.